The Linden to Mabura Hill Road Project is now 89 per cent complete, with the contractor expected to meet a December 8, 2026 deadline for its full completion.

This was disclosed by Minister of Public Works Juan Edghill during the Committee of Supply on Monday as he answered questions regarding the Government’s request for additional money to pump into the project. Linden to Mabura Hill Road Project is the first phase of the much larger Linden to Lethem Road Project. Under Phase One, some 121 kilometres (km) of asphalt road is being built from Linden to Mabura Hill.

These works are being carried out by Brazilian-based contractor, Álya Construtora – an international infrastructure company specialising in civil works, heavy infrastructure projects and road development in complex environments. The contractor was initially expected to wrap up works by the end of August 2026 but the project has faced several setbacks. Nonetheless, Edghill informed that the new deadline is now December 8, 2026.

“If they go past the 8th of December, clauses of the contract will be invoked which will include liquidated damages,” the Minister cautioned.

Nevertheless, as construction on this first section nears completion, the Guyana Government is already moving towards the next phase, which will see some 30-kilometres (km) of road from Mabura to Kurupukari being upgraded. In fact, reports indicate that a contract has already been signed with the same company to execute this second phase. On Monday, Edghill explained that the $4.77 billion which the Government was seeking for the project was intended to accelerate construction of the additional 30 kilometers beyond Mabura Hill.

“We’ve been able to engage the contractor at the same 2021 rate to push another 30 kilometres. So, we’re now moving from Mabura Hill, 30 kilometres forward, and heading to the Kurupukari Bridge,” the minister highlighted.

Meanwhile, the Linden to Mabura Hill phase is being done to the tune of US$190 million and is funded through the Caribbean Development Bank (CDB) via a US$112 million loan, a grant of £50 million (US$66 million) from the United Kingdom Caribbean Infrastructure Fund (UKCIF), and an input of US$12 million from the Guyana Government.

Currently, the Linden to Lethem road network is being utilised by an estimated 50,000 travellers who transport goods from the coast to the inland regions of Guyana and even into neighbouring Brazil. The previous condition of this road had posed significant challenges for commuters and transport operators. Heavily laden lorries frequently toppled off the roadway, and deteriorated bridges required manual alignment of boards for crossings, often with unsafe outcomes. However, when completed into an all-weather road, this pertinent piece of infrastructure would significantly improve connectivity, reduce travel time and open up new commercial and trade opportunities especially between Guyana and Brazil.

 

---