Households in Linden, Region Ten (Upper Demerara-Berbice), pay GY$5 per kilowatt-hour (kWh) for electricity, while the State pays as much as GY$63 per kWh to procure the power.

This was disclosed on Monday by Minister of Public Utilities and Aviation Deodat Indar during the Committee of Supply, where he faced scrutiny over the government’s request for $11.3 billion to cover fuel costs for State-run power companies across the country.

The Guyana Power and Light Inc. (GPL), which supplies electricity mainly along the coastal plain from Charity in Region Two to Moleson Creek in Region Six, sought and got approved $8 billion to cover the cost of fuel.

Meanwhile, the Linden Electricity Company Inc (LECI) received approval for $2.4 billion; Mabaruma Power and Light Company Inc some $328 million; Mahdia Power and Light Company some $186 million; Port Kaituma Power and Light Company Inch. Some $264 million; Moruca Power and Light some $49 million, Matthew’s Ridge Power and Light Company Inc. some $10 million, and the Hinterland Electrification Company Inc. some $4 million.

Regarding the provisions for LECI, Indar explained that about $4.8 billion was budgeted but now the government needs $2.4 billion more to cover the costs for fuel.

The minister disclosed that the LECI purchases power from Bosai Minerals Group at around GY$54-$63 per kWh and sells at around GY$5 per kWh for households and $12 for businesses.

He also disclosed that electricity is supplied to a distribution cooperative at just $1 per kWh.

According to Indar, electricity demand in Linden is driven by approximately 13,000 customers and the consumption of about 16,000 streetlights.

According to an August 2026 report, most GPL customers are receiving power from the national grid at $43.43 per kWh for residential use and $56.38 per kWh for commercial use.

Officials have said despite the rising costs for fuel, consumers have not seen increases in their monthly bills.

Meanwhile, in June this year, the government announced that electricity rates in Bartica, Region Seven (Cuyuni-Mazaruni) would be slashed by 25 per cent – a move that benefitted over 5000 consumers.

In fact, the government has already started to introduce cuts to electricity rates for some villages where there is solar-powered energy. President Dr Irfaan Ali explained a few months ago that these reductions are part of the government’s commitment to slash electricity rates by 50 per cent when the Gas-to-Energy project becomes fully operational next year.

The GtE project will see natural gas being piped from the Stabroek Block offshore to the Wales, West Bank Demerara, site where a Natural Gas Liquids (NGL) facility and a 300-megawatt combined-cycle power plant are currently being built.

The project is expected to deliver 57 megawatts (MW) of natural gas-powered electricity by year-end and that it will be fully operational by early 2027.

---

Discover more from INews Guyana

Subscribe to get the latest posts sent to your email.

Previous articleNo 3rd power ship, but 20MW of generating capacity secured – Indar