US$5B needed to modernise Guyana’s electricity transmission, distribution network – Jagdeo

0
VP Dr Bharrat Jagdeo speaking at the GMSA 31st Annual Presentation Awards Ceremony at the Guyana Marriott Hotel, Kingston, on Thursday evening

Guyana will need nearly US$5 billion to modernise and expand its electricity transmission and distribution infrastructure as demand continues to increase, Vice President (VP) Dr Bharrat Jagdeo has said.

Speaking on Thursday at the Guyana Manufacturing and Services Association’s (GMSA) 31st Annual Presentation Awards Ceremony at the Guyana Marriott Hotel, Kingston, Jagdeo outlined the scale of investments required to support the country’s growing electricity needs.

He said peak electricity demand has increased from 130 megawatts (MW) in 2019 to 216MW in recent days, while available generation capacity has grown from 115MW to 255MW over the same period.

The number of customers on the Guyana Power and Light (GPL) database has also increased from 184,000 in 2019 to 231,000.

Jagdeo attributed the higher demand to increased household incomes, greater ownership of appliances, the installation of air conditioning in homes and the expansion of businesses.

He said the electricity system must be fundamentally upgraded to accommodate that growth.

A major component of the Government’s plans is the Gas-to-Energy (GtE) Project, which Jagdeo acknowledged has experienced significant delays and increased costs.

He said the revised timeline places completion of the single-cycle unit at the end of the first quarter of 2027, with the combined-cycle unit expected to be completed around June.

Addressing the circumstances surrounding the delays, Jagdeo disclosed that the Government and the contractor had disputed claims relating to the access road and site preparation works.

He said the company had claimed that the road, for which ExxonMobil was responsible during the pre-project period, was not completed on time and was of poor quality. The company also claimed that additional work was required for site preparation.

Dispute Adjudication Board

Jagdeo said the Government disputed those claims and initially considered pursuing arbitration following an award by the Dispute Adjudication Board (DAB).

However, he explained that arbitration could have taken several more years and resulted in additional delays.

The Government therefore decided to pursue a negotiated settlement, he said, noting that importing fuel to generate the equivalent of the 300MW expected from the gas project could cost more than US$300 million annually.

Jagdeo said avoiding further delays was important given the potential cost to the country.

He also defended the Government’s decision to maintain electricity rates at US$0.23 per kilowatt-hour despite increasing generation costs.
According to the VP, the cost of generating electricity stood at US$0.33 per kilowatt-hour in 2025 and increased to US$0.3456 this year, largely because of higher fuel costs.

He said the Government subsidised electricity consumers by approximately $23 billion in 2024 and $33 billion in 2025.

In addition to those subsidies, capital support for electricity infrastructure amounted to $24 billion last year and is projected to reach $62 billion this year.

Jagdeo said the combined subsidy for 2025 amounted to approximately $94 billion, covering both the cost of maintaining electricity prices and investments in infrastructure.

He further explained that electricity generated at the GtE facility would be sold to GPL at an estimated US$0.05 per kilowatt-hour.
He said this would be significantly lower than GPL’s current generation costs.

The project’s financial projections, he added, did not include potential revenue from the sale of natural gas liquids (NGLs).
On the operation of the facilities, Jagdeo said Siemens had been contracted to operate and maintain the power plant under a long-term agreement.

He also disclosed that the Government was close to concluding an agreement with a United States company to operate the NGL facility.
Apart from generation, Jagdeo said substantial investments would be required to strengthen the transmission and distribution networks.
He said contracts had already been awarded for sections of the transmission backbone, including a $422 million contract for infrastructure extending towards the West Bank Demerara area and another contract valued at approximately $160 million for works extending towards Kuru Kururu.

The wider transmission backbone is estimated to cost approximately US$2.3 billion, while another US$2.5 billion would be required for distribution infrastructure.

The distribution programme would involve replacing transformers and upgrading approximately 1500 kilometres of the network.
Jagdeo said existing lines were becoming overloaded as consumers added more electrical equipment to their homes and businesses, contributing to instability in the system.

He explained that the current network also lacks sufficient redundancy, meaning damage to a utility pole in one location could affect electricity supply across a wider area.

The VP said the modernisation programme was necessary to support a modern economy and reduce the risk of widespread power interruptions.

He also disclosed plans to construct a 40MW power plant in Mexico, which would operate using liquefied natural gas, as part of efforts to address electricity needs in locations including Bartica and Lethem.

Natural gas liquids

On the natural gas liquids component, Jagdeo said the Government was working on arrangements for storage and other facilities, including a bottling plant.

He said a company was being structured with a proposed ownership arrangement under which the Government would retain 50 per cent of the shares in trust, 30 per cent would be allocated to institutional investors and 20 per cent to ordinary Guyanese investors.

Jagdeo said the proposed arrangement would include a guaranteed 10 per cent return for Guyanese institutional investors, while ordinary investors would receive 30 per cent.

He said the Government expected the arrangements to allow liquefied petroleum gas prices to be reduced by 50 per cent.

Jagdeo acknowledged that the scale of the electricity expansion programme meant that some projects would experience delays but urged the private sector and the public to recognise the extent of the work required.

He maintained that expanding generation capacity and modernising the transmission and distribution networks were necessary to meet the country’s growing electricity demand.

 

---