At least 11 contracts awarded under the Education Ministry were terminated this year after contractors failed to execute the agreed works.
This was disclosed on Wednesday by the Attorney General’s Chambers and Legal Affairs Ministry, which noted that the terminations were carried out after being examined by its Contract Review Unit.
Contracts for the construction of a students’ dormitory, multipurpose hall and kitchen at Monkey Mountain, Region Eight (Potaro-Siparuni), Lots 1 and 2, which were awarded to K’s Trucking and Construction, were terminated on June 29, 2026. Those contracts were terminated because the contractor failed to execute works and had insufficient financial, technical, and human resource capacity.
Another contract awarded for the construction of a female dorm at the Kwakwani Secondary School, Region 10 (Upper Demerara-Bebrice), to Rahaman Construction and Transportation Services was terminated on March 10, 2026, after the contractor failed to commence and execute the works, failed to mobilise adequate resources, and was consistently noncompliant with contractual obligations.
Modular Construction Services had its contract for the design and build for the reconstruction of the Kwakwani Secondary School terminated on July 8, 2026, for failing to commence and execute works.
Additionally, the contract for Lot 2 for the extension of the Dora Secondary School, Kuru Kuru, Linden Highway, which was awarded to 4S Security and Building Enterprise, was terminated on March 10, 2026, over the company’s failure to mobilise adequate resources, its non-responsiveness to official correspondence, and its failure to take corrective action.
A contract for the construction of the Karasabai Secondary School Region Nine (Upper Takutu-Upper Essequibo) awarded to Avinash Contracting and Scrap Metal Inc was terminated on October 30, 2026, over the firm’s failure to execute the works in accordance with the approved programme, as well as delays beyond the contractual limit.
D&S Construction, which was awarded a contract to construct the Vreed-en-Hoop Secondary School Lot 2, Blocs 2 and 3, was pulled from the project on October 27, 2026 for poor progress and inadequate resources.
Also terminated was a contract to LS Contracting Services for the extension of a staffroom at the Stewartville Secondary School, a contract to Jemcorp Engineering and Imports for the construction and furnishing of home economics and industrial technology labs at St Cuthberts Mission, and a contract to Rawl Davis Contracting Services for the rehabilitation of the Wiruni Nursery School – no reasons were provided for those terminations.
Meanwhile, Sheriff Construction Inc had its contract terminated on November 5, 2026, for the construction of a students’ dormitory at Jawalla, Region Seven (Cuyuni-Mazaruni). According to the Ministry, the $310 million contract was awarded on October 16, 2024, works commenced in December 2024, and the project was expected to be completed in October 2025.
However, the contractor requested an extension of time until February 2026, but the project remained at six per cent progress, “indicating significant delays in execution”, according to the Ministry.
“To date, payments comprise a mobilisation advance of $46 million and an Interim Payment Certificate (IPC) payment of $7 million, from which $3.6 million was deducted,” the Ministry noted with regard to the Jawalla dorm project.
Meanwhile, Blueprint Builders Inc. had its contract for the construction of Lot 2 of the multipurpose hall and kitchen at Kopinnang, North Pakaraimas, terminated on November 5, 2026, for similar reasons.
According to the Ministry, the $149 million contract was awarded on March 1, 2025, with a completion deadline of November 1, 2026; however, after some seven months had elapsed, the project was only six per cent completed.
“An advance payment of $52 million was made, with mobilisation security provided by Assuria on 28th February 2026 and performance security on 26th August 2026. However, after approximately seven and a half months had elapsed, only six per cent of the works had been completed, indicating significant delays in project execution. In view of the unsatisfactory progress, termination of the contract is recommended,” the Ministry noted.
Speaking on the matter during his programme “Issues in the News” on Tuesday, Attorney General Anil Nandlall emphasised that in addition to the termination of the contracts, the Government will be filing legal action against contractors, where necessary.
“The requisite legal steps will now be taken; legal proceedings will be filed if that is the opinion of members of our Review Team; and proceedings will claim the necessary compensatory remedies. They will claim damages for breach of contract, they will claim losses of different types, and of course, they will seek to recover liquidated damages and other punitive sanctions where the contracts so provide,” Nandlall said.
He assured the public that the Government is policing “all public contracts, and we are taking steps when we find breaches occurring.”